Motions
2 and 3
Councillors D. Keating
and F. McCarthy
An
Environmental Impact Study will be carried out on the Greater Lucan Area
prior to the start of any construction specifically associated with any
phase of Adamstown. This is to assess the impact of the total Adamstown
SDZ planning scheme. It will also consider the Greater Dublin Area, in as
much as it is directly impacted by the Adamstown SDZ Planning Scheme.
The
recommendations from this EIS will be included in the development and
phasing of the final Adamstown SDZ Planning Scheme.
The terms
of reference of the Environmental Impact Study will be the subject of
consultation and formal agreement with the
councillors.
Response
of the County Manager
The Draft Planning Scheme
was prepared in accordance with the relevant legislative requirements
under Part IX of the Planning and Development Act 2000.
Part IX, Section 168 (3)
details the requirements for information required on any likely
significant impacts on the environment for a Draft Planning Scheme for
residential development, which is not an EIS.
The Draft Planning Scheme
includes an Environmental Appraisal in accordance with the requirements of
Section 168 (3). The
Environmental Appraisal was prepared by Independent Consultants, Arup
Consulting.
The technical and
legislative purposes of an EIS are to assess the environmental impacts of
a specific project or proposal, for which a full design has been
completed, rather than for a masterplan such as the Draft Planning
Scheme.
It remains the case that a
full EIS will be required in respect of future planning applications for
development above relevant minimum threshold size within the Adamstown
SDZ. For example, a housing
development of 500 units or more will require a full
EIS.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 2 and 3 not be
adopted.
Motions
4 and 5
Councillors D. Keating
and F. McCarthy
Section
4.2.5, Phase 1A, Add an additional consideration which requires completion
at this phase:
“Provision
of an operational bus route servicing Adamstown at peak
hours;”.
Response
of the County Manager
The issue
of ‘operational capacity of service’ has been given significant
consideration as a result of public consultation, particularly with regard
to the provision of public transport services such as bus
routes.
In the legislative context of
an SDZ Planning Scheme, it has been concluded that on balance, public
transport provision must relate to the provision of land, facilities
and/or infrastructure.
The inclusion of operational
capacity (i.e. specification of a bus route) would render the Draft
Planning Scheme highly difficult to implement and in particular, would
introduce an element outside the control of the Planning Authority or
commercial developers/landowners.
The
detailed implementation of a key aspect of the Draft Planning Scheme would
therefore be in the hands of third parties, who may not have any
motivation or interest in the development of Adamstown.
The Motion
would introduce a range of new variables and a major degree of uncertainty
into the Draft Planning Scheme, which would severely reduce the ability of
the Planning Authority to secure the implementation of the Draft Planning
Scheme:-
·
The Draft Planning
Scheme must be implemented through the operation of development control
procedures (i.e. the submission of planning applications) within the
existing physical planning system.
·
The proposal to
require a bus service after 400 dwelling units does not balance a quantum
of development with proposals for transportation in a viable
manner.
·
Bus levels of service
and routes vary and may be increased and withdrawn by operators in
response to public demand or other factors.
·
It is possible that
bus services could be provided to satisfy the phasing requirements of the
Draft Planning Scheme and withdrawn on receipt of planning
permission.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 4 and 5 not be
adopted.
Motions
6 and 7
Councillors D. Keating
and F. McCarthy
Section 4.2.6, Phase
1B, insert the following condition to those requiring completion at this
phase:
“Adamstown Rail
Service, with a confirmed peak hour operational capacity for 600 embarking
passengers per hour, in the direction of the peak traffic
flow.
Response
of the County Manager
The issue
of ‘operational capacity of service’ has been given significant
consideration as a result of public consultation, particularly with regard
to the provision of public transport such as rail
services.
In the legislative context of
an SDZ Planning Scheme, it has been concluded that on balance, public
transport provision must relate to the provision of land, facilities
and/or infrastructure.
It remains the case that
Phase 1B requires the completion of a railway station at Adamstown. Initial capacity at the Station is
projected to be 600 passengers per hour in each direction.
The inclusion of operational
capacity (i.e. specification of rail capacity) in phasing would render the
Draft Planning Scheme highly difficult to implement and in particular,
would introduce an element outside the control of the Planning Authority
or commercial developers/landowners.
The
provision of land, fixed infrastructure and/or facilities is a more
tangible and therefore workable measure of control, particularly where
development is balanced with proposals for transportation in a viable
manner.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 6 and 7 not be
adopted.
Motions
8 and 9
Councillors D. Keating
and F. McCarthy
Section
4.2.6, Phase 1B, insert the following condition to those requiring
completion:
“A bus
route servicing the Adamstown Railway Station with a confirmed peak hour
operational capacity of at
least 400 people per hour in the direction of the peak traffic flow.
”
Response
of the County Manager
The issue
of ‘operational capacity of service’ has been given significant
consideration as a result of public consultation, particularly with regard
to the provision of public transport services such as bus
routes.
In the legislative context of
an SDZ Planning Scheme, it has been concluded that on balance, public
transport provision must relate to the provision of land, facilities
and/or infrastructure.
The inclusion of operational
capacity (i.e. specification of a bus route) would render the Draft
Planning Scheme highly difficult to implement and in particular, would
introduce an element outside the control of the Planning Authority or
commercial developers/landowners.
The
provision of land, fixed infrastructure and/or facilities is a more
tangible and therefore workable measure of control, particularly where
development is balanced with proposals for transportation in a viable
manner.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 8 and 9 not be
adopted.
Motions
10 and 11
Councillors D. Keating
and F. McCarthy
Section
4.2.7, Phase 2, amend the following condition, which requires completion
of Primary School #1 to the following:
Permanent construction
of Primary School #1 with a minimum of 18 no. classrooms and with a
capacity for at least 544 children, and to facilitate pupil teacher ratios
not exceeding standards specified by the Department of Education, and with
an operational capacity to service the number of pupils at Adamstown, as
calculated from Central Statistics Office statistics for family sizes and
children of schoolgoing ages.
Response
of the County Manager
The issue
of ‘operational capacity of service’ has been given significant
consideration as a result of public consultation, particularly with regard
to school provision.
In the legislative context of
an SDZ Planning Scheme, it has been concluded that on balance, school
provision must relate to the provision of land, facilities and/or
infrastructure to a standard acceptable to the Department of
Education.
It remains the case that
Phase 2 of the Draft Planning Scheme requires the provision of the first
school at Adamstown. The
Draft Scheme therefore requires that a site be secured and a school
established.
The location and size of
proposed school sites is acceptable to the Department of
Education.
The inclusion of operational
capacity (i.e. specification of greater than an initial minimum number of
classrooms or pupil-teacher ratios etc.) in phasing would render the Draft
Planning Scheme highly difficult to implement and in particular, would
introduce an element outside the control of the Planning Authority or
commercial developers/landowners.
The
provision of land, fixed infrastructure and/or facilities is a more
tangible and therefore workable measure of control, particularly where
development is balanced with proposals for school provision in a viable
manner.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 10 and 11 not be
adopted.
Motions
12 and 13
Councillors D. Keating
and F. McCarthy
Section
4.2.8, Phase 3, insert an additional condition which requires completion:
“The
upgrade of the N4 including the R120 Newcastle Road N4 junction, and the
upgraded N4-M50 junction;”
Response
of the County Manager
Improvements to the N4
and the M50 are part of the National Road network and are under the
control of the National Roads Authority. The development of Adamstown is
not dependent on improvements to the National Road
network.
The
development of Adamstown is dependent on the following key transportation
elements:-
·
Adamstown Link Road
(Adamstown – Outer Ring Road);
·
Celbridge Link Road
(Adamstown – Celbridge Road);
·
Improved links at the
two points where Tandy’s land currently enters and exits the SDZ
lands;
·
A new link from within
the Adamstown SDZ direct to the rear of the Superquinn District
Centre;
·
Improvements to the
R120 Newcastle Road;
·
A new railway station
with transport interchange facilities;
·
Four tracking of the
Dublin-Kildare Railway Line;
·
Two new QBCs
(Adamstown – N4 QBC and Adamstown - ORR QBC);
·
A comprehensive
network of roads, busways, pedestrian and cycle routes, including road
crossing points, car and bicycle parking, within the SDZ
lands.
The required up-front
provision of transportation infrastructure has been balanced with a viable
quantum of development permissible at each stage of proposed
phasing.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 12 and 13 not be
adopted.
Motions
14 and 15
Councillors D. Keating
and F. McCarthy
Section
4.2.9, Phase 4, insert the condition which requires completion:
“Adamstown Railway
Station, with a confirmed peak hour operational capacity for, in the
region of 3000 passengers, in the direction of the peak traffic flow, together with park and ride
facilities to a finished standard”
Response
of the County Manager
The issue
of ‘operational capacity of service’ has been given significant
consideration as a result of public consultation, particularly with regard
to the provision of public transport such as rail
services.
In the legislative context of
an SDZ Planning Scheme, it has been concluded that on balance, public
transport provision must relate to the provision of land, facilities
and/or infrastructure.
It remains the case that
Phase 5 requires the completion of the four-tracking of the railway line
serving Adamstown Station. After four-tracking, capacity at Adamstown is
projected to be 3,000 passengers per hour in each direction.
The inclusion of operational
capacity (i.e. specification of rail capacity) in phasing would render the
Draft Planning Scheme highly difficult to implement and in particular,
would introduce an element outside the control of the Planning Authority
or commercial developers/landowners.
The
provision of land, fixed infrastructure and/or facilities is a more
tangible and therefore workable measure of control, particularly where
development is balanced with proposals for transportation in a viable
manner.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 14 and 15 not be
adopted.
Motions
16 and 17
Councillors D. Keating
and F. McCarthy
Section
4.2.10, Phase 5, amend the condition which requires completion of the QBC
on Loop Road #2 to the following:
“The
dedicated QBC busway on Loop Road #2 with a confirmed peak hour
operational capacity of 600 people per hour, in the direction of the peak
traffic flow.”
Response
of the County Manager
The issue
of ‘operational capacity of service’ has been given significant
consideration as a result of public consultation, particularly with regard
to the provision of public transport such as bus
services.
In the legislative context of
an SDZ Planning Scheme, it has been concluded that on balance, public
transport provision must relate to the provision of land, facilities
and/or infrastructure.
It remains the case that
Phase 5 requires a dedicated QBC busway on the central spine road/loop
road #2. The busway will have
a capacity that is significantly in excess of 600 people per hour in each
direction.
The inclusion of operational
capacity (i.e. specification of bus capacity) in phasing would render the
Draft Planning Scheme highly difficult to implement and in particular,
would introduce an element outside the control of the Planning Authority
or commercial developers/landowners.
The
provision of land, fixed infrastructure and/or facilities is a more
tangible and therefore workable measure of control, particularly where
development is balanced with proposals for transportation in a viable
manner.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 16 and 17 not be
adopted.
Motions
18 and 19
Councillors D. Keating
and F. McCarthy
Section 4.2.7, Phase
2, amend the following
condition which requires completion:
“Permanent
construction of at least the first phase of a Secondary School with a
minimum of 18 no. classrooms, with a capacity for at least 544 children
and to facilitate pupil teacher ratios not exceeding standards specified
by the Department of Education, and with an operational capacity to
service the number of pupils at Adamstown, as calculated from Central
Statistics Office statistics for family sizes and children of schoolgoing
ages.
Response
of the County Manager
The issue
of ‘operational capacity of service’ has been given significant
consideration as a result of public consultation, particularly with regard
to school provision.
In the legislative context of
an SDZ Planning Scheme, it has been concluded that on balance, school
provision must relate to the provision of land, facilities and/or
infrastructure to a standard acceptable to the Department of
Education.
It remains the case that
Phase 4 of the Draft Planning Scheme requires the provision of a second
school at Adamstown. The
Draft Scheme therefore requires that a site be secured and a school
established.
The location and size of
proposed school sites is acceptable to the Department of
Education.
The inclusion of operational
capacity (i.e. specification of greater than an initial minimum number of
classrooms or pupil-teacher ratios etc.) in phasing would render the Draft
Planning Scheme highly difficult to implement and in particular, would
introduce an element outside the control of the Planning Authority or
commercial developers/landowners.
The
provision of land, fixed infrastructure and/or facilities is a more
tangible and therefore workable measure of control, particularly where
development is balanced with proposals for school provision in a viable
manner.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 18 and 19 not be
adopted.
Motions
20 and 21
Councillors D. Keating
and F. McCarthy
Section 4.2.9?, Phase
4, insert the condition which requires completion of the following
condition:
“Permanent
construction of Primary School #2 with a minimum of 18 no. classrooms and
with a capacity for at least 544 children, and to facilitate pupil teacher
ratios not exceeding standards specified by the Department of Education,
and with an operational capacity to service service the number of pupils
at Adamstown, as calculated from Central Statistics Office statistics for
family sizes and children of schoolgoing ages
Response
of the County Manager
The issue
of ‘operational capacity of service’ has been given significant
consideration as a result of public consultation, particularly with regard
to school provision.
In the legislative context of
an SDZ Planning Scheme, it has been concluded that on balance, school
provision must relate to the provision of land, facilities and/or
infrastructure to a standard acceptable to the Department of
Education.
It remains the case that
Phase 6 of the Draft Planning Scheme requires the provision of a third
school at Adamstown. The
Draft Scheme therefore requires that a site be secured and a school
established.
The location and size of
proposed school sites is acceptable to the Department of
Education.
The inclusion of operational
capacity (i.e. specification of greater than an initial minimum number of
classrooms or pupil-teacher ratios etc.) in phasing would render the Draft
Planning Scheme highly difficult to implement and in particular, would
introduce an element outside the control of the Planning Authority or
commercial developers/landowners.
The
provision of land, fixed infrastructure and/or facilities is a more
tangible and therefore workable measure of control, particularly where
development is balanced with proposals for school provision in a viable
manner.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 20 and 21 not be
adopted.
Motions
22 and 23
Councillors D. Keating
and F. McCarthy
Section 4.2.11, Phase
6, amend the condition which requires completion of Primary school #2 to
the following:
“Permanent construction of Primary
School #3 with a minimum of 18 no. classrooms and with a capacity for at
least 544 children, and to facilitate pupil teacher ratios not exceeding
standards specified by the Department of Education, and with an
operational capacity to service service the number of pupils at Adamstown,
as calculated from Central Statistics Office statistics for family sizes
and children of schoolgoing ages.
Insert the condition
which requires completion of the following
condition:
Permanent
construction of an extension to Secondary School #1(or additional
building) to provide an additional
minimum no of
classrooms with capacity to service the number of pupils at
Adamstown, as calculated from Central Statistics Office statistics for
family sizes and children of schoolgoing ages.
Response
of the County Manager
The issue
of ‘operational capacity of service’ has been given significant
consideration as a result of public consultation, particularly with regard
to school provision.
In the legislative context of
an SDZ Planning Scheme, it has been concluded that on balance, school
provision must relate to the provision of land, facilities and/or
infrastructure to a standard acceptable to the Department of
Education.
It remains the case that
Phase 8 of the Draft Planning Scheme requires the provision of a fourth
school at Adamstown. The
Draft Scheme therefore requires that a site be secured and a school
established.
The location and size of
proposed school sites is acceptable to the Department of
Education.
The inclusion of operational
capacity (i.e. specification of greater than an initial minimum number of
classrooms or pupil-teacher ratios etc.) in phasing would render the Draft
Planning Scheme highly difficult to implement and in particular, would
introduce an element outside the control of the Planning Authority or
commercial developers/landowners.
The
provision of land, fixed infrastructure and/or facilities is a more
tangible and therefore workable measure of control, particularly where
development is balanced with proposals for school provision in a viable
manner.
Recommendation of the
County Manager
For the above reasons
it is recommended that motions 22 and 23 not be adopted.
Motions
24 and 25
Councillors D. Keating
and F. McCarthy
Amend
Adamstown Castle & Somerton development areas, characterised as low
density to be controlled and characterised as follows:
·
Min-Max
perimeter building height: 2-3 storeys in total, with up to 3 storeys in
total at corner/feature buildings.
·
Landmark
buildings no higher than 4 stories in total.
Amend all tables and
figures associated with detailing these development areas accordingly.
Response
of the County Manager
Proposed
building height in the Draft Planning Scheme is related to the scale of
streets and public space adjoining and to the need for a satisfactory
ratio of built enclosure in the public realm according to the principles
of urban design.
It is
necessary for the Draft Planning Scheme to detail minimum and maximum
building height. This does
not mean that maximum permissible building height is required in all
cases. Building height will
be assessed in the context of residential amenity as part of any future
planning applications for development.
It has
already been proposed in the Manager’s Report on Submissions received
(March 2003) to adjust maximum storey heights in all Development Areas
immediately adjoining existing housing as follows:-
The maximum
height of courtyard buildings shown hatched on the attached map (March
2003 report) is reduced to a maximum of two storeys at any point and the
maximum height of perimeter buildings shown hatched on the attached map is
reduced to not more three storeys with four storeys at corners and/or
feature buildings.
The
proposed change addresses the areas where maximum building height may be
an issue and relates to part of five separate Development Areas. The proposed Motion relates to two
entire Development Areas, without regard for the internal design and
layout of streets and spaces.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 25 and 26 not be adopted.
Motions
26 and 27
Councillors D. Keating
and F. McCarthy
Amend all phases to
require that: Prior to the
commencement of a phase, an EIS be completed, taking into account the
totality of development detailed in the DPS for that phase.
Response
of the County Manager
Planning and Development
legislation clearly specifies the types and thresholds of development for
which an EIS may be required.
It remains the case that a
full EIS will be required in respect of future planning applications for
development above relevant minimum threshold size within the Adamstown
SDZ. For example, a housing
development of 500 units or more will require a full
EIS.
Recommendation of the
County Manager
For the
above reasons it is recommended that motions 26 and 27 not be
adopted.
Motion
28
Councillor F.
McCarthy.
That the
proposed site for the Fire Station be moved to a location in closer
proximity to the Railway Station and away from existing
housing.
Report of the County
Manager
There is no
confirmed requirement for a fire station in this area at present. Should a site be required in the
future, Dublin Fire Brigade are satisfied that the proposed site at
Adamstown would be a suitable location.
A fire
station in Adamstown would serve the wider Lucan-Clondalkin area in
addition to the SDZ lands.
The fire station site is therefore located proximate to the main
road network and the existing built-up area.
Any future
fire station building on the identified site would be approximately 100m
from the nearest dwellinghouse and must be subject to a full planning
application.
It
is proposed in the Manager’s Report on submissions of March 2003 that the
draft planning scheme be amended to specify that:-
The proposed fire station
site shall be levelled, grassed and seeded to form an area of public open
space, pending determination of the need for a fire station in this area
and selection of this site for such a facility. This work should comprise part of
the development of the adjoining ‘Somerton’ development area and phased
accordingly. Should it be
determined by Dublin Fire Brigade and the Planning Authority that the site
is not required for a fire station, it may be developed for ‘courtyard’
housing in accordance with this Planning Scheme.
Recommendation of the
County Manager
For the
above reasons it is recommended that motion 28 not be adopted.
|